Burgess Hill
Location
Burgess Hill
Client
Croudace & Hydrock Consultants
Value
£500k+
Duration
11 weeks
Quantity
- 98,000m3 of material removed from surcharge to bring it to the agreed level
- 38,000m3 of backfill
- 60,000m3 stockpile
- 3,500m3 stabilisation of slurry
Overview
Barton were contracted for earthworks on a prestigious project for a development of high-end residential housing and associated infrastructure which has been ongoing for several years.
The scope of works was to remove approximately 98,000m3 of surcharge material. Approximately 38,000m3 of this was placed in the Public Open Space to bring it to the agreed level. 60,000m3 of material was stockpiled elsewhere.
Excavation of Pond Slurry 3,500m3, which required modification and stabilisation to produce an engineering fill material that met the specification and could be reused on site to reduce the vast quantity of import required.
Installation of a Toe Drain to client specification in the Public Open Space to allow the area to be free draining.
Barton installed a road crossing to protect live services during works and also provided and installed settlement monitoring equipment for the clients ongoing monitoring of the site.
All works were surveyed by our in-house engineers.
Scope of work:
- Pond Slurry – Excavate, stabilise and place material from the existing drainage pond in the POS
- Removal of surcharge to POS
- Temporary road crossing with appropriate protection on a live surface
- Installation of 4 rod settlement gauges
- Site welfare
- Survey topsoil stockpile