Swindon – White Hart Junction Improvements
Location
Swindon
Client
Geoffrey Osborne Limited
Duration
1 week
Quantity
- 1,200 m2 of RoadCem
Overview
Barton were contracted by Geoffrey Osborne Ltd to complete a earthworks and stabilisation package for improvements at White Hart Junction (A419/A420 interchange), for Swindon Borough Council.
Following contracted topsoil strip back and stockpile for later use, we
Completed 1,200m2 of stabilisation using a blend of RoadCem and Cement, with min 150mm imported Type 1 to create the required wearing course.
Barton have partnered with PowerCem Technologies to become the preferred UK installer of RoadCem™.
RoadCem™ is a stabilisation additive which has been specially developed for application in road building and hydraulic engineering, utilising a fine blend of powdered zeolites that enables binding with almost any kind of materials.
If you have a requirement for any earthworks, ground engineering, civils or plant maintenance, please contact Barton on 01536 722100 or email reception@barton.co.uk