Thurleigh Airfield
Location
Thurleigh Airfield
Client
GF Tomlinson
Value
£900k+
Duration
20 weeks
Quantity
- Site strip 14,000 m3,
- Cut/Fill 15,000m3,
- Recycle Type1 8,900m3,
- Soil stabilisation 73,000m2 (30%CBR in-situ Stabilisation Sub-base replacement)
Overview
Barton Plant were appointed by GF Tomlinson to carry out earthworks, processing of concrete hard standings to produce recycle Type 1 and soil stabilisation on site at Thurleigh Airfield.
The project was for the construction of a Vehicle Repair Centre and Storage Facility. Works are being done over two Phases. The First phase has been completed fully to the Clients satisfaction with the view to remobilise to site in July to complete remaining works.